In fact, there was a greater challenge later. The adaptation project is different from a new one. The old equipment could be disassembled only after shut-down but it must start-up on time. Therefore, the commissioning time is shortened. We adopted a series of measures to ensure the smooth commissioning.
We arranged Mr. Lincoln Zhuang, our Project Manager & Service Engineer, and Mr. William Wu, the Senior Project Manager to go to NCFC in advance, checking the situation and providing the necessary services and instructions to make a better preparation for the coming of European engineers.
After arrived at NCFC plant, European engineers found the installation progress was not so good, so they took time to check the wiring, test hydraulic units and worked overtime every night. Finally, we overcame the disadvantages of the installation company such as non-ideal installation progress, wrong wiring, deformation of original frame, difficult installation and adjustment for the rails, improper adjustment for some valves and difficult adjustment of the new and old shims, finally ensured the start-up and operation requirements.